Orange Street & Meadowbrook Sewer Replacement and Tumbleweed Lift Station Improvements

Description:

This project involved the rehabilitation and modernization of the sanitary sewer infrastructure for the Town of Pecos City, Texas, improving the reliability and operational capacity of the wastewater collection and pumping system.

The scope included replacing sanitary sewer mains along Orange Street and Meadowbrook, installing new manholes, connecting to existing utilities, and constructing a new force main serving the Tumbleweed Lift Station. The lift station was upgraded with a new flow meter vault, concrete equipment foundations, backup generator, electrical improvements, perimeter fencing, and other supporting infrastructure to provide a more reliable and efficient wastewater system.

Eng:

West Texas Consultants, Inc. (WTC)

Eng Project Manager:

David M. Young, Jr., P.E.

Parties Involved:

Total Contract Amount:

$1,610,936.41

Client:

Town of Pecos City

Location:

Pecos, Reeves County, Texas

Client:

Town of Pecos City

Location:

Pecos, Reeves County, Texas

Eng:

West Texas Consultants, Inc. (WTC)

Eng Project Manager:

David M. Young, Jr., P.E.

Parties Involved:

Total Contract Amount:

$1,610,936.41