top of page
2147 Utility Extension
Description:
The 2147 Utility Extension Project involved the extension and connection of potable water and sanitary sewer infrastructure to provide service to a new area. The scope included installing an 8-inch PVC C900 water main, connection valves, a fire hydrant, and air/vacuum valves. Sanitary improvements included the installation of a 2-inch force main, tie-ins to the existing system, gate valves, and related fittings.
Additional work included tree protection, silt fencing, stabilized construction entrances, rock berm installation, curb removal and reconstruction, and full-depth asphalt pavement repairs, delivering a fully serviced and operational utility extension.
Eng:
Eng Project Manager:
Parties Involved:
Total Contract Amount:
$63,202.00
Client:
Location:
Marble Falls
Completion Date:
July 28, 2013
Client:
Location:
Marble Falls
Completion Date:
July 28, 2013
Eng:
Parties Involved:
Total Contract Amount:
$63,202.00
bottom of page