top of page
CR 170
Description:
The CR 170 Storm Drainage Improvements Project involved the construction and rehabilitation of stormwater infrastructure to improve runoff management and roadway safety. The scope included large-scale excavation, removal of existing infrastructure, installation of 18-inch and 24-inch reinforced concrete pipe (RCP), and the construction and adjustment of storm manholes, inlets, and grates.
Additional work included structure relocations, alignment adjustments, and restoration of disturbed surfaces, delivering a more efficient and reliable drainage system along the corridor.
Eng:
Eng Project Manager:
Parties Involved:
Total Contract Amount:
$477,520.88
Client:
Location:
Completion Date:
September 22, 2015
Client:
Location:
Completion Date:
September 22, 2015
Eng:
Parties Involved:
Total Contract Amount:
$477,520.88